Semar doubles prices in the construction of a naval hospital in Coatzacoalcos


MEXICO CITY.

The Mexican Navy-Navy Secretariat (Semar) must clarify the whereabouts of 7 million 787 thousand 620.86 pesos that they were not checked in the audits carried out on the Construction and Equipment of a Naval General Hospital in Coatzacoalcos, Veracruz, where various irregularities were detected, such as overpayments, duplication of unit prices and pieces of reinforcement in stairs that were not placed.

According to the report of the Superior Audit of the Federation (ASF), overpayments of 1 million 799 thousand pesos in the concept of wooden formwork no. EXCIM-051 due to duplication of items in the unit prices and the basic prices of materials and labor used, as well as excessively low yields (7.0 m2 per day).

In turn, payments in excess for 417 thousand 800 pesos in concept no. ALBM-15-1: 4 / INT “Intermediate concrete block wall of 15 x 20 x 40 centimeters in 15 centimeters thick”, in the review of the unit price it was observed that horizontal stair reinforcements were considered for every three courses that They were not placed and within the price basics, wire rod that was not used was considered.

Also they overpayments for 420 thousand 700 pesos in the CIMCB-250 concept “Concrete in foundation f’c = 250 kg / cm2 premixed in normal resistance poured with pump …”, because in the unit price the slump surcharge was considered twice.

Other payments in excess are for an amount of 142 thousand 500 weights in concept no. “CIMMALALEC-6×6-10 / 10” Enabled supply and placement of electrowelded steel mesh 6×6 10/10 … “, due to the fact that the unit price considered a too low labor yield (56.5 m2 per day) .

Overpayments for 204 thousand 500 pesos in concept no. EXCONMR-35 “Construction of concrete floor to rupture MR 35, pumped 15 cm thick …”, because the concrete was poured directly from the mixer truck without using the specified concrete pump, so Nor did the slump surcharge considered apply; and differences between the estimated volumes of work and those physically verified from the visit to the work for 4 million 803 thousand 100 pesos in 31 work concepts related to masonry, plastering, waterproofing, hauling of materials, Hydrosanitary and electrical installations, and Wastewater Treatment Plant, among others.

Photo: Cuartocuro

The Superior Audit of the Federation (ASF) determined that Semar must clarify 7 million 787 thousand 620.86 pesos were spent on that you still do not have the tax receipts.

Of 10 results, in one no irregularity was detected, 3 were solved by the audited entity before the issuance of this Report and the remaining 6 generated 6 Observations Sheets.

Overpayments of 1,799.0 thousand pesos in the concept of wooden formwork no. EXCIM-051 due to duplication of items in the unit prices and the basic prices of materials and labor used, as well as excessively low yields (7.0 m2 per day).

Overpayments of 417.8 thousand pesos in concept no. ALBM-15-1: 4 / INT “Intermediate concrete block wall of 15 x 20 x 40 cm in 15 cm thickness”, in the review of the unit price it was observed that horizontal stair reinforcements were considered for every three courses that They were not placed and within the price basics, wire rod that was not used was considered.

Overpayments for 420.7 thousand pesoss in the CIMCB-250 concept “Concrete in foundations f’c = 250 kg / cm2 premixed in normal resistance poured with pump …”, because the unit price was considered twice the slump surcharge.

Overpayments of 142.5 thousand pesos in concept no. “CIMMALALEC-6×6-10 / 10” Enabled supply and placement of electrowelded steel mesh 6×6 10/10 … “, due to the fact that the unit price considered a too low labor yield (56.5 m2 per day) .

Overpayments of 204.5 thousand of weights in concept no. EXCONMR-35 “Construction of concrete floor to rupture MR 35, pumped 15 cm thick …”, because the concrete was poured directly from the mixer truck without using the specified concrete pump, so neither did the slump surcharge considered apply.

Differences between the estimated work volumes and those physically verified during the work visit for 4,803.1 thousand pesos in 31 construction concepts related to masonry, plastering, waterproofing, hauling of materials, hydrosanitary and electrical installations, and the Wastewater Treatment Plant, among others.

YOU MAY ALSO BE INTERESTED IN:

He takes a serenade and ends up crying inconsolably when he sees that she has a boyfriend

Belinda effect; Matador Hernández makes fun of his boyfriends’ tattoos

Chris Evans accidentally publishes his ‘pack’ on Instagram

Karla Panini recreates video of cake girls and is criticized for ruining it

The trick to keep lemons fresh and in good condition for 3 months!

How to detect hidden cameras in bedrooms with your cell phone

Woman asks to delete her stepson from family photo and destroy her in networks

They reveal photos of Yolanda Andrade and Verónica Castro kissing on the mouth

Visit our Galleries

jvc




www.excelsior.com.mx